RESULTS
For the first Equipment & PPE point, the requests were:
- Periodic verification (at least quarterly) of PPE and equipment
- Review Management and Assignment of Fire Extinguishers
- Different PPE according to processes (ex. Asphalts)
For the second subcontract management point:
- Required greater controls on the quality of subcontract work;
- Request to reduce subcontract work during periods of low work Delivery.
For the third 360° Training point:
- Training on the management system (XME);
- Training on Customer systems;
- Internal training.
- Streamlining procedure for materials requests
For the fourth Technical Regulations point:
- Provide Technical Specifications (including updates);
- Related training courses.
For the fifth point:
- Lack of correspondence between physical stock and system stock
- Streamline the Material Requests procedure
For the sixth point:
- Foreman communication
- PMG (control by both AT and CS)
- Daily accounting (measurement, system loading, accounting)